HAI DI LAO

DETAILS

CLIENT: HAI DI LAO HOT POT

SIZE (SQ FT): 12,000

PROGRAMME PERIOD: 16 WEEKS

VALUE: £5,200,000

DESCRIPTION

This project involved the fit out of a restaurant over the basement and ground floor at Unit 4/5 Trocadero for a Chinese ‘hot pot’ restaurant.

    • New MEPH services (new AHUs, chillers)

    • New kitchen area, private dining suites, a nail bar, as well as relevant front of house (promotional) and back of house (admin) areas

    • New shop fronts were installed to the main entrance on Coventry Street as well as a secondary entrance, accessible via the tube entrance

    • A new feature stair access was created from basement to ground

    • 2nr new lifts installed

    • All new joinery installed on both levels (a large majority of which was manufactured in China and installed in the UK)


OUR WORK ETHIC

We thoroughly believe that each project is a joint venture, we are only as capable as the sum of our parts (from design teams through to our management team and supply chain). The best way to ensure we are all able to achieve our collective goals is to work collectively, collaboratively, part of a team. This team ethic has ensured we are able to build up a client-base, a consultant-base, a subcontractor-base and a supplier-base that understands, and shares, our working principles.


WORK WITH US

If you are starting a new project or have any questions about our services and experience, please get in touch today.